Notable Project: CarTech’s Dual Station ESR Furnace bus tubes
Carpenter Technologies - Latrobe, PA

Problem: The retrofit and rebuild of Carpenter Technologies’ dual station ESR furnace bus tubes took some finesse. The ESR is an older furnace built circa 1960, and consequently sourcing spare components and the craftsmanship to perform the work is difficult.
Solution: The replacement bus tube components arrived at the customer’s facility on time, and were installed during the 2019 summer shutdown. All components fit correctly. Bam!
Eager to solve problems, I2r POWER’s technical team is more than willing to help you unravel your challenges.
Have questions about this topic?
More Articles
Power Cable Donation to Kent State enhances student experience
Power Cable Donation to Kent State enhances student experience I2r POWER recently provided two new sets of water-cooled power cables to the foundry and metal casting facility at Kent State University’s College of Aeronautics and […]
Read MoreEnd-of-Year Holidays Time to Express Gratitude
End-of-Year Holidays Time to Express Gratitude It’s time to celebrate a successful, though at times difficult, year! We made it! The company holiday party is an ideal time to share our gratitude for all those […]
Read MoreElectromagnetic caster stirrer designs vary depending on use
Electromagnetic caster stirrer designs vary depending on use Electromagnetic stirrers for steel applications produce very low frequency, high amplitude magnetic fields to agitate steel when molten. Steel applications include ladle stirring and stirring in continuous […]
Read More